Process Step | Date Initiated | Date Completed | Comments |
Received | 12/17/2018 | 12/17/2018 |
|
WMR Request | 12/27/2018 | 3/18/2019 |
|
Transfer Initial Comment Period | 1/1/2019 | 1/31/2019 |
|
Final Order Issued | 4/4/2019 | 4/4/2019 |
|
CBU Received | 4/29/2020 | 4/29/2020 |
|
Proof to the Satisfaction | 6/30/2020 | 6/30/2020 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|