Process Step | Date Initiated | Date Completed | Comments |
Received | 12/17/2018 | 12/17/2018 |
|
WMR Request | 12/27/2018 | 3/27/2019 |
|
GW Review Request | 12/27/2018 | 3/14/2019 |
|
Transfer Initial Comment Period | 1/1/2019 | 1/31/2019 |
|
Draft PD Issued | 6/19/2019 | 6/19/2019 |
|
PD Weekly Public Notice | 10/1/2019 | 10/1/2019 |
|
PD Issued | 10/1/2019 | 10/1/2019 |
|
Final Order Issued | 11/7/2019 | 11/7/2019 |
|
CBU Received | 4/7/2020 | 4/7/2020 |
|
Certificate Confirming Issued | 9/3/2020 | 9/3/2020 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|