Process Step | Date Initiated | Date Completed | Comments |
Received | 12/28/2018 | 12/28/2018 |
|
Reimbursement Authority | 12/28/2018 | |
|
Reimbursement Authority | 12/28/2018 | |
|
WMR Request | 1/7/2019 | 1/10/2019 |
|
GW Review Request | 1/7/2019 | 2/13/2019 |
|
Transfer Initial Comment Period | 1/8/2019 | 2/7/2019 |
|
RA Applicant Agreement | 1/29/2019 | 1/29/2019 |
|
Draft PD Issued | 3/28/2019 | 4/16/2019 |
|
PD Issued | 6/21/2019 | 6/21/2019 |
|
PD Weekly Public Notice | 6/25/2019 | 6/25/2019 |
|
Final Order Issued | 8/28/2019 | 8/28/2019 |
|
CBU Completeness Review | 10/18/2021 | 10/20/2021 |
|
CBU Received | 10/18/2021 | 10/18/2021 |
|
Certificate Confirming Issued | 5/12/2023 | 5/12/2023 |
|