| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/23/2019 | 1/23/2019 |
|
| WMR Request | 1/28/2019 | 1/29/2019 |
|
| Transfer Initial Comment Period | 1/29/2019 | 2/28/2019 |
|
| Draft PD Issued | 3/19/2019 | 3/19/2019 |
|
| PD Issued | 12/20/2019 | 12/20/2019 |
|
| PD Weekly Public Notice | 12/24/2019 | 12/24/2019 |
|
| Final Order Issued | 2/10/2020 | 2/10/2020 |
|
| CBU Due | 2/10/2021 | 2/10/2021 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| Certificate Remaining Issued | 2/23/2023 | 2/23/2023 |
RR Cert 94753 issued supersedes cert 83738
|