Process Step | Date Initiated | Date Completed | Comments |
Received | 2/13/2019 | 2/13/2019 |
|
WMR Request | 2/15/2019 | 7/5/2019 |
|
Transfer Initial Comment Period | 2/19/2019 | 3/21/2019 |
|
Draft PD Issued | 11/8/2019 | 11/8/2019 |
|
PD Issued | 2/18/2020 | 2/18/2020 |
|
PD Weekly Public Notice | 2/25/2020 | 2/25/2020 |
|
Final Order Issued | 4/2/2020 | 4/2/2020 |
|
Certificate Remaining Issued | 4/2/2020 | 4/2/2020 |
RR Cert 94805 Issued supersedes 54521
|
Certificate Remaining Issued | 4/2/2020 | 4/2/2020 |
RR Cert 94804 Issued supersedes Cert 27462
|
Certificate Remaining Issued | 4/2/2020 | 4/2/2020 |
RR Cert 94803 Issued supersedes 8718
|
CBU Completeness Review | 1/13/2021 | 1/19/2021 |
|
CBU Received | 1/13/2021 | 1/13/2021 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Certificate Confirming Issued | 1/27/2023 | 1/27/2023 |
|