Process Step | Date Initiated | Date Completed | Comments |
Received | 4/22/2019 | 4/22/2019 |
|
WMR Request | 4/25/2019 | 5/3/2019 |
|
GW Review Request | 4/25/2019 | 4/29/2019 |
|
Transfer Initial Comment Period | 4/30/2019 | 5/30/2019 |
|
Draft PD Issued | 6/21/2019 | 6/21/2019 |
|
PD Weekly Public Notice | 10/1/2019 | 10/1/2019 |
|
PD Issued | 10/1/2019 | 10/1/2019 |
|
Final Order Issued | 11/13/2019 | 11/13/2019 |
|
CBU Received | 12/26/2019 | 12/26/2019 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
Certificate Confirming Issued | 4/8/2022 | 4/8/2022 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|