Process Step | Date Initiated | Date Completed | Comments |
Received | 7/23/2019 | 7/23/2019 |
|
WMR Request | 7/29/2019 | 7/31/2019 |
|
Transfer Initial Comment Period | 7/30/2019 | 8/29/2019 |
|
Deficiency Letter | 9/17/2019 | 9/17/2019 |
|
Draft PD Issued | 10/17/2019 | 10/30/2019 |
|
PD Weekly Public Notice | 11/19/2019 | 11/19/2019 |
|
PD Issued | 11/19/2019 | 11/19/2019 |
|
Final Order Issued | 1/10/2020 | 1/10/2020 |
|
CBU Received | 5/4/2020 | 5/4/2020 |
|
Certificate Confirming Issued | 7/31/2020 | 7/31/2020 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|