Process Step | Date Initiated | Date Completed | Comments |
Received | 7/29/2019 | 7/29/2019 |
|
WMR Request | 7/31/2019 | 9/12/2019 |
|
Transfer Initial Comment Period | 8/6/2019 | 9/5/2019 |
|
Draft PD Issued | 1/13/2020 | |
|
PD Issued | 3/12/2020 | 3/12/2020 |
|
PD Weekly Public Notice | 3/17/2020 | 3/17/2020 |
|
Final Order Issued | 5/14/2020 | 5/14/2020 |
|
CBU Completeness Review | 9/24/2020 | 10/2/2020 |
|
CBU Received | 9/24/2020 | 9/24/2020 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Certificate Confirming Issued | 1/27/2023 | 1/27/2023 |
|