| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/23/2019 | 9/23/2019 |
|
| WMR Request | 9/25/2019 | 11/4/2019 |
|
| GW Review Request | 9/25/2019 | 3/2/2021 |
|
| Transfer Initial Comment Period | 10/1/2019 | 10/31/2019 |
|
| Draft PD Issued | 6/7/2021 | 6/7/2021 |
|
| PD Issued | 9/14/2021 | 9/14/2021 |
|
| PD Weekly Public Notice | 9/21/2021 | 9/21/2021 |
|
| Final Order Issued | 11/10/2021 | 11/10/2021 |
|
| Certificate Remaining Issued | 11/10/2021 | 11/10/2021 |
RR Cert 95915 Issued supersedes Cet 92120
|
| CBU Received | 6/21/2022 | 6/21/2022 |
|
| Certificate Confirming Issued | 1/27/2023 | 1/27/2023 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|