| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/15/2019 | 10/15/2019 |
|
| WMR Request | 10/23/2019 | 10/24/2019 |
|
| Transfer Initial Comment Period | 10/29/2019 | 11/28/2019 |
|
| Draft PD Issued | 1/28/2020 | 1/28/2020 |
|
| PD Issued | 3/12/2020 | 3/12/2020 |
|
| PD Weekly Public Notice | 3/17/2020 | 3/17/2020 |
|
| Final Order Issued | 4/23/2020 | 4/23/2020 |
|
| Certificate Remaining Issued | 4/23/2020 | 4/23/2020 |
RR Cert 94946 Issued supersedes Cert 42579
|
| Certificate Remaining Issued | 4/23/2020 | 4/23/2020 |
RR Cert 94947 Issued supersedes 44240
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Completeness Review | 11/10/2021 | 1/28/2022 |
|
| CBU Received (Partial) | 11/10/2021 | 11/10/2021 |
|
| CBU Received | 11/10/2021 | 11/10/2021 |
|
| CBU Completeness Review | 1/28/2022 | 1/28/2022 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 6/2/2023 | 6/2/2023 |
|