Process Step | Date Initiated | Date Completed | Comments |
Received | 11/6/2019 | 11/6/2019 |
|
WMR Request | 11/14/2019 | 12/11/2019 |
|
Transfer Initial Comment Period | 11/19/2019 | 12/19/2019 |
|
Final Order Issued | 1/16/2020 | 1/16/2020 |
|
Extension Application Received | 7/30/2021 | 7/30/2021 |
|
Extension FO Issued | 8/18/2021 | 8/18/2021 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
Extended Completion Date [Extension C Date] | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
CBU Received | 10/3/2022 | 10/3/2022 |
|
Proof to the Satisfaction | 3/1/2023 | 3/1/2023 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|