| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/6/2019 | 12/6/2019 |
|
| WMR Request | 12/10/2019 | 3/23/2020 |
|
| ODFW Review | 12/10/2019 | 2/11/2020 |
|
| Transfer Initial Comment Period | 12/17/2019 | 1/16/2020 |
|
| Draft PD Issued | 2/18/2021 | 2/18/2021 |
|
| PD Issued | 5/11/2021 | 5/11/2021 |
|
| PD Weekly Public Notice | 5/18/2021 | 5/18/2021 |
|
| Final Order Issued | 7/8/2021 | 7/8/2021 |
|
| CBU Received | 4/11/2022 | 4/11/2022 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 12/16/2022 | 12/16/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|