Process Step | Date Initiated | Date Completed | Comments |
Received | 12/13/2019 | 12/13/2019 |
|
Transfer Initial Comment Period | 1/7/2020 | 2/6/2020 |
|
WMR Request | 1/7/2020 | 4/1/2020 |
|
GW Review Request | 1/7/2020 | 5/21/2020 |
|
GW Review Request | 6/23/2020 | 7/31/2020 |
|
Draft PD Issued | 10/8/2020 | 10/8/2020 |
|
PD Issued | 12/24/2020 | 12/24/2020 |
|
PD Weekly Public Notice | 12/29/2020 | 12/29/2020 |
|
Final Order Issued | 2/10/2021 | 2/10/2021 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Received | 11/3/2022 | 11/3/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|