Process Step | Date Initiated | Date Completed | Comments |
Received | 12/19/2019 | 12/19/2019 |
|
GW Review Request | 1/6/2020 | 3/5/2020 |
|
WMR Request | 1/6/2020 | 3/18/2020 |
|
Transfer Initial Comment Period | 1/7/2020 | 2/6/2020 |
|
Reimbursement Authority | 1/27/2020 | 9/22/2020 |
|
Deficiency Letter | 1/28/2020 | 9/22/2020 |
|
RA Applicant Agreement | 2/28/2020 | 2/28/2020 |
|
RA Applicant Agreement | 7/31/2020 | 7/31/2020 |
|
Final Order Issued | 9/22/2020 | 9/22/2020 |
|
Permit Superseding Issued | 9/22/2020 | 9/22/2020 |
Permit G-18414 Issued supersedes G-13880
|