Process Step | Date Initiated | Date Completed | Comments |
Received | 1/15/2020 | 1/15/2020 |
|
WMR Request | 1/22/2020 | 4/14/2020 |
|
GW Review Request | 1/22/2020 | 4/7/2020 |
|
Transfer Initial Comment Period | 1/28/2020 | 2/27/2020 |
|
PD Issued | 6/1/2022 | 6/1/2022 |
|
PD Weekly Public Notice | 6/7/2022 | 6/7/2022 |
|
Final Order Issued | 8/18/2022 | 8/18/2022 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Received | 5/20/2024 | 5/20/2024 |
|
Certificate Confirming Issued | 9/27/2024 | 9/27/2024 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|