| Process Step | Date Initiated | Date Completed | Comments |
| GW Review Request | 3/18/2020 | 3/14/2021 |
|
| Received | 3/18/2020 | 3/18/2020 |
|
| WMR Request | 3/18/2020 | 3/19/2020 |
|
| Transfer Initial Comment Period | 3/24/2020 | 4/23/2020 |
|
| Deficiency Letter | 8/6/2021 | 8/7/2021 |
|
| ODFW Review | 8/11/2021 | 9/7/2021 |
|
| Draft PD Issued | 9/8/2021 | 9/14/2021 |
|
| News $ Due Letter | 10/7/2021 | 10/12/2021 |
|
| PD Issued | 10/27/2021 | 10/27/2021 |
|
| PD Weekly Public Notice | 11/2/2021 | 11/2/2021 |
|
| Certificate Remaining Issued | 1/3/2022 | 1/3/2022 |
RR Cert 95999 issued supersedes Cert 28656
|
| Final Order Issued | 1/3/2022 | 1/3/2022 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|
| CBU Received | 10/10/2024 | 10/10/2024 |
|