| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/17/2020 | 4/17/2020 |
|
| Reimbursement Authority | 4/17/2020 | 5/25/2021 |
|
| WMR Request | 5/21/2020 | 6/4/2020 |
|
| GW Review Request | 5/21/2020 | 12/1/2020 |
|
| Transfer Initial Comment Period | 5/26/2020 | 6/25/2020 |
|
| RA Applicant Agreement | 10/9/2020 | 10/9/2020 |
|
| News $ Due Letter | 3/13/2021 | 3/17/2021 |
|
| Permit Superseding Issued | 5/25/2021 | 5/25/2021 |
Permit G-18516 Issued supersedes Permit G-16407
|
| Final Order Issued | 5/25/2021 | 5/25/2021 |
|