Process Step | Date Initiated | Date Completed | Comments |
Received | 4/23/2020 | 4/23/2020 |
|
WMR Request | 4/29/2020 | 5/29/2020 |
|
GW Review Request | 4/29/2020 | 9/23/2020 |
|
Transfer Initial Comment Period | 5/12/2020 | 6/11/2020 |
|
Deficiency Letter | 12/29/2020 | 12/29/2020 |
|
Draft PD Issued | 1/28/2021 | 2/3/2021 |
|
News $ Due Letter | 2/25/2021 | 3/4/2021 |
|
PD Issued | 3/18/2021 | 3/18/2021 |
|
PD Weekly Public Notice | 3/23/2021 | 3/23/2021 |
|
Final Order Issued | 5/19/2021 | 5/19/2021 |
|
Certificate Remaining Issued | 5/19/2021 | 5/19/2021 |
RR Cert 95540 issued supersedes Certificate 88113
|
Certificate Remaining Issued | 5/19/2021 | 5/19/2021 |
RR Cert 95539 issued supersedes Certificate 87897
|
Certificate Remaining Issued | 5/19/2021 | 5/19/2021 |
RR Cert 95538 issued supersedes Certificate 83328
|
Certificate Remaining Issued | 5/19/2021 | 5/19/2021 |
RR Cert 95537 issued supersedes Certificate 33176
|
Certificate Remaining Issued | 5/19/2021 | 5/19/2021 |
RR Cert 95536 issued supersedes Certificate 22847
|
CBU Received | 9/16/2022 | 9/16/2022 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|