Process Step | Date Initiated | Date Completed | Comments |
Received | 4/20/2020 | 4/20/2020 |
|
WMR Request | 4/29/2020 | 7/9/2020 |
|
GW Review Request | 4/29/2020 | 6/24/2020 |
|
Transfer Initial Comment Period | 5/12/2020 | 6/11/2020 |
|
Draft PD Issued | 3/31/2021 | 3/31/2021 |
|
PD Issued | 5/11/2021 | 5/11/2021 |
|
PD Weekly Public Notice | 5/18/2021 | 5/18/2021 |
|
Final Order Issued | 6/30/2021 | 6/30/2021 |
|
Certificate Remaining Issued | 6/30/2021 | 6/30/2021 |
RR cert 95810 issued supersedes Cert 68116
|
CBU Received | 11/17/2023 | 11/17/2023 |
|
Certificate Confirming Issued | 4/26/2024 | 4/26/2024 |
|
Certificate Confirming Issued | 9/6/2024 | 9/6/2024 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|