| Process Step | Date Initiated | Date Completed | Comments | 
			
				| Received | 5/18/2020 | 5/18/2020 | 
                                                    
                                                 | 
			
				| WMR Request | 5/27/2020 | 6/4/2020 | 
                                                    
                                                 | 
			
				| GW Review Request | 5/27/2020 | 9/21/2021 | 
                                                    
                                                 | 
			
				| Transfer Initial Comment Period | 6/2/2020 | 7/2/2020 | 
                                                    
                                                 | 
			
				| Deficiency Letter | 6/19/2020 | 6/26/2020 | 
                                                    
                                                 | 
			
				| Final Order Issued | 11/10/2021 | 11/10/2021 | 
                                                    
                                                 | 
			
				| Permit Superseding Issued | 11/10/2021 | 11/10/2021 | 
                                                    Permit G-18727 issued supersedes permit G-17077
                                                 |