| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/22/2020 | 5/22/2020 |
|
| Reimbursement Authority | 5/22/2020 | 1/7/2021 |
|
| Transfer Initial Comment Period | 6/9/2020 | 7/9/2020 |
|
| WMR Request | 6/9/2020 | 7/16/2020 |
|
| ODFW Review | 6/9/2020 | 7/8/2020 |
|
| RA Applicant Agreement | 6/24/2020 | 6/24/2020 |
|
| Draft PD Issued | 9/10/2020 | 9/10/2020 |
|
| PD Issued | 11/18/2020 | 11/18/2020 |
|
| PD Weekly Public Notice | 11/24/2020 | 11/24/2020 |
|
| Final Order Issued | 1/7/2021 | 1/7/2021 |
|
| Final Order Issued | 2/4/2021 | 2/4/2021 |
|
| Certificate Remaining Issued | 2/4/2021 | 2/4/2021 |
RR Cert 95227 Issued supersedes Cert 22691
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Received | 1/23/2023 | 1/23/2023 |
|
| Certificate Confirming Issued | 9/22/2023 | 9/22/2023 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|