Process Step | Date Initiated | Date Completed | Comments |
Received | 6/9/2020 | 6/9/2020 |
|
WMR Request | 6/9/2020 | 10/28/2020 |
|
Transfer Initial Comment Period | 6/16/2020 | 7/16/2020 |
|
GW Review Request | 7/6/2020 | 8/5/2021 |
|
Deficiency Letter | 10/19/2021 | 1/18/2022 |
|
Draft PD Issued | 3/2/2022 | 5/20/2022 |
|
News $ Due Letter | 7/13/2022 | 8/18/2022 |
|
PD Issued | 10/31/2022 | 10/31/2022 |
|
PD Weekly Public Notice | 11/1/2022 | 11/1/2022 |
|
Certificate Remaining Issued | 3/14/2023 | 3/14/2023 |
RR 96626 Issued Supersedes Cert 35750
RR 96627 Issued Supersedes Cert 48608
RR 96628 Issued Supersedes Cert 94357
RR 96629 Issued Supersedes Cert 94359
RR 96630 Issued Supersedes Cert 94361
RR 96631 Issued Supersedes Cert 94362
RR 96632 Issued Supersedes Cert 94365
|
Final Order Issued | 3/14/2023 | 3/14/2023 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|