Process Step | Date Initiated | Date Completed | Comments |
Received | 6/5/2020 | 6/5/2020 |
|
Transfer Initial Comment Period | 6/16/2020 | 7/16/2020 |
|
WMR Request | 6/16/2020 | 7/6/2020 |
|
ODFW Review | 6/16/2020 | 8/26/2020 |
|
Deficiency Letter | 10/5/2020 | 12/10/2020 |
|
Draft PD Issued | 1/21/2021 | 2/5/2021 |
|
News $ Due Letter | 3/29/2021 | 4/5/2021 |
|
PD Issued | 5/5/2021 | 5/5/2021 |
|
PD Weekly Public Notice | 5/11/2021 | 5/11/2021 |
|
Final Order Issued | 7/21/2021 | 7/21/2021 |
|
Completion Due (C Date) | 7/21/2021 | 7/21/2021 |
RR Cert 95525 Issued supersedes Cert 48403
|
Certificate Remaining Issued | 7/21/2021 | 7/21/2021 |
RR Cert 95521 Issued supersedes Cert 7716
|
Certificate Remaining Issued | 7/21/2021 | 7/21/2021 |
RR Cert 95522 Issued supersedes Cert 9045
|
Certificate Remaining Issued | 7/21/2021 | 7/21/2021 |
RR Cert 95523 Issued supersedes Cert 9046
|
Certificate Remaining Issued | 7/21/2021 | 7/21/2021 |
RR Cert 95524 Issued supersedes Cert 9311
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|