Process Step | Date Initiated | Date Completed | Comments |
Received | 7/10/2020 | 7/10/2020 |
|
WMR Request | 7/16/2020 | 7/21/2020 |
|
GW Review Request | 7/16/2020 | 9/28/2023 |
|
Transfer Initial Comment Period | 7/21/2020 | 8/20/2020 |
|
Draft PD Issued | 11/23/2020 | 12/15/2020 |
|
PD Issued | 3/3/2021 | 3/3/2021 |
|
PD Weekly Public Notice | 3/9/2021 | 3/9/2021 |
|
Final Order Issued | 10/24/2023 | 10/24/2023 |
|
CBU Received | 11/4/2024 | 11/4/2024 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|