Process Step | Date Initiated | Date Completed | Comments |
Reimbursement Authority | 11/2/2020 | 11/18/2021 |
|
Transfer Initial Comment Period | 11/24/2020 | 12/24/2020 |
|
WMR Request | 11/24/2020 | 1/5/2021 |
|
Received | 11/24/2020 | 11/24/2020 |
|
ODFW Review | 11/24/2020 | 1/8/2021 |
|
RA Applicant Agreement | 12/22/2020 | 12/22/2020 |
|
Draft PD Issued | 5/15/2021 | 5/15/2021 |
|
Draft PD Issued | 7/21/2021 | 7/21/2021 |
REVISED DPD
|
PD Issued | 10/12/2021 | 10/12/2021 |
|
PD Weekly Public Notice | 10/19/2021 | 10/19/2021 |
|
Final Order Issued | 11/18/2021 | 11/18/2021 |
|
Completion Due (C Date) | 10/1/2027 | 10/1/2027 |
|
CBU Due | 10/1/2028 | 10/1/2028 |
|