| Process Step | Date Initiated | Date Completed | Comments |
| Transfer Initial Comment Period | 12/8/2020 | 1/7/2021 |
|
| WMR Request | 12/10/2020 | 2/16/2021 |
|
| Received | 12/10/2020 | 12/10/2020 |
|
| Certificate Remaining Issued | 3/31/2021 | 3/31/2021 |
RR Cert 95602 Issued supersedes 34827
|
| Certificate Remaining Issued | 3/31/2021 | 3/31/2021 |
RR Cert 95603 Issued supersedes Cert 47029
|
| Final Order Issued | 3/31/2021 | 3/31/2021 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|