Process Step | Date Initiated | Date Completed | Comments |
Received | 12/23/2020 | 12/23/2020 |
|
WMR Request | 12/23/2020 | 12/23/2020 |
|
Transfer Initial Comment Period | 12/29/2020 | 1/28/2021 |
|
PD Issued | 1/23/2023 | 1/23/2023 |
|
PD Weekly Public Notice | 1/24/2023 | 1/24/2023 |
|
Certificate Remaining Issued | 2/23/2023 | 2/23/2023 |
RR Cert 96863 issued supersedes cert 40901
|
Final Order Issued | 2/23/2023 | 2/23/2023 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|