Process Step | Date Initiated | Date Completed | Comments |
Received | 1/4/2021 | 1/4/2021 |
|
WMR Request | 1/25/2021 | 4/1/2021 |
|
Transfer Initial Comment Period | 1/26/2021 | 2/25/2021 |
|
Draft PD Issued | 2/24/2022 | 2/24/2022 |
|
PD Issued | 5/11/2022 | 5/11/2022 |
|
PD Weekly Public Notice | 5/17/2022 | 5/17/2022 |
|
Final Order Issued | 6/22/2022 | 6/22/2022 |
|
Certificate Remaining Issued | 6/22/2022 | 6/22/2022 |
RR Cert 96199 issued supersedes cert 14632
|
CBU Received | 6/28/2023 | 6/28/2023 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|