Process Step | Date Initiated | Date Completed | Comments |
Received | 1/4/2021 | 1/4/2021 |
|
WMR Request | 1/25/2021 | 4/23/2021 |
|
Transfer Initial Comment Period | 1/26/2021 | 2/25/2021 |
|
Draft PD Issued | 9/22/2021 | 9/22/2021 |
|
News $ Due Letter | 9/27/2021 | 1/31/2022 |
|
PD Issued | 11/9/2021 | 11/9/2021 |
|
PD Weekly Public Notice | 11/16/2021 | 11/16/2021 |
|
Final Order Issued | 1/31/2022 | 1/31/2022 |
|
Certificate Remaining Issued | 1/31/2022 | 1/31/2022 |
RR Cert 96020 issued supersedes Cert 4903
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|
CBU Received | 10/8/2024 | 10/8/2024 |
|