Process Step | Date Initiated | Date Completed | Comments |
GW Review Request | 2/2/2021 | 2/15/2024 |
|
Received | 2/2/2021 | 2/2/2021 |
|
WMR Request | 2/2/2021 | 2/2/2021 |
|
Transfer Initial Comment Period | 2/9/2021 | 3/11/2021 |
|
Draft PD Issued | 12/18/2024 | 12/18/2024 |
|
News $ Due Letter | 1/27/2025 | 2/3/2025 |
|
PD Issued | 2/19/2025 | 2/19/2025 |
|
PD Weekly Public Notice | 2/25/2025 | 2/25/2025 |
|
Certificate Remaining Issued | 4/9/2025 | 4/9/2025 |
RR 98179 Issued Supersedes CERT 50503
|
Final Order Issued | 4/9/2025 | 4/9/2025 |
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|