Process Step | Date Initiated | Date Completed | Comments |
Received | 2/25/2021 | 2/25/2021 |
|
Transfer Initial Comment Period | 3/23/2021 | 4/22/2021 |
|
WMR Request | 3/23/2021 | 5/13/2021 |
|
GW Review Request | 3/23/2021 | 8/29/2022 |
|
Reimbursement Authority | 10/29/2021 | 4/5/2023 |
|
RA Applicant Agreement | 1/19/2022 | 1/19/2022 |
|
Draft PD Issued | 10/27/2022 | 12/14/2022 |
|
News $ Due Letter | 1/23/2023 | 2/6/2023 |
|
PD Issued | 2/22/2023 | 2/22/2023 |
|
PD Weekly Public Notice | 2/28/2023 | 2/28/2023 |
|
Re-Assigned New Number | 4/5/2023 | 4/5/2023 |
RR 97010 Issued Supersedes Cert 86436
|
Final Order Issued | 4/5/2023 | 4/5/2023 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|