| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/17/2021 | 3/17/2021 |
|
| WMR Request | 3/24/2021 | 4/13/2021 |
|
| GW Review Request | 3/24/2021 | 2/15/2024 |
|
| Transfer Initial Comment Period | 3/30/2021 | 4/29/2021 |
|
| Draft PD Issued | 8/5/2024 | 10/8/2024 |
|
| News $ Due Letter | 10/10/2024 | |
|
| PD Issued | 12/11/2024 | 12/11/2024 |
|
| PD Weekly Public Notice | 12/17/2024 | 12/17/2024 |
|
| Certificate Remaining Issued | 2/5/2025 | 2/5/2025 |
RR 98045 Issued Supersedes CERT 95299
|
| Final Order Issued | 2/5/2025 | 2/5/2025 |
|
| Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
| CBU Due | 10/1/2027 | 10/1/2027 |
|