| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/15/2021 | 3/15/2021 |
|
| WMR Request | 3/24/2021 | 5/20/2021 |
|
| ODFW Review | 3/24/2021 | 5/13/2021 |
|
| Transfer Initial Comment Period | 3/30/2021 | 4/29/2021 |
|
| Reimbursement Authority | 8/2/2021 | 7/14/2022 |
|
| RA Applicant Agreement | 8/31/2021 | 8/31/2021 |
|
| Draft PD Issued | 1/27/2022 | 1/27/2022 |
|
| PD Issued | 4/26/2022 | 4/26/2022 |
|
| PD Weekly Public Notice | 5/3/2022 | 5/3/2022 |
|
| Final Order Issued | 7/14/2022 | 7/14/2022 |
|
| PD Weekly Public Notice | 7/26/2022 | 7/26/2022 |
|
| PD Weekly Public Notice | 7/26/2022 | 7/26/2022 |
|
| Final Order Issued | 9/20/2022 | 9/20/2022 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|
| CBU Received | 3/3/2025 | 3/3/2025 |
|