| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/26/2021 | 3/26/2021 |
|
| Transfer Initial Comment Period | 4/6/2021 | 5/6/2021 |
|
| WMR Request | 4/6/2021 | 5/4/2021 |
|
| GW Review Request | 4/6/2021 | 4/7/2021 |
|
| Deficiency Letter | 4/15/2021 | 4/21/2021 |
|
| News $ Due Letter | 7/2/2021 | 7/30/2021 |
|
| Permit Superseding Issued | 11/10/2021 | 11/10/2021 |
Permit G-18675 Issued supersedes Permit G-17297
|
| Final Order Issued | 11/10/2021 | 11/10/2021 |
|