Process Step | Date Initiated | Date Completed | Comments |
Received | 4/23/2021 | 4/23/2021 |
|
Reimbursement Authority | 4/23/2021 | 3/24/2022 |
|
WMR Request | 5/3/2021 | 5/7/2021 |
|
GW Review Request | 5/3/2021 | 6/11/2021 |
|
Transfer Initial Comment Period | 5/4/2021 | 6/3/2021 |
|
RA Applicant Agreement | 5/25/2021 | 5/25/2021 |
|
Draft PD Issued | 8/24/2021 | 8/24/2021 |
|
PD Issued | 2/1/2022 | 2/1/2022 |
|
PD Weekly Public Notice | 2/8/2022 | 2/8/2022 |
|
Final Order Issued | 3/25/2022 | 3/25/2022 |
|
CBU Received | 8/1/2022 | 8/1/2022 |
|
Certificate Confirming Issued | 1/27/2023 | 1/27/2023 |
|
Completion Due (C Date) | 10/1/2027 | 10/1/2027 |
|
CBU Due | 10/1/2028 | 10/1/2028 |
|