| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/10/2021 | 5/10/2021 |
|
| WMR Request | 5/24/2021 | 6/23/2021 |
|
| GW Review Request | 5/24/2021 | 9/29/2023 |
|
| Transfer Initial Comment Period | 5/25/2021 | 6/24/2021 |
|
| Draft PD Issued | 6/27/2024 | 6/27/2024 |
|
| PD Issued | 9/13/2024 | 9/13/2024 |
|
| PD Weekly Public Notice | 9/17/2024 | 9/17/2024 |
|
| Certificate Remaining Issued | 10/22/2024 | 10/22/2024 |
RR 97891 Issued Supersedes CERT 57771
|
| Final Order Issued | 10/22/2024 | 10/22/2024 |
|
| Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
| CBU Due | 10/1/2027 | 10/1/2027 |
|