Process Step | Date Initiated | Date Completed | Comments |
Received | 6/7/2021 | 6/7/2021 |
|
WMR Request | 6/23/2021 | 6/2/2023 |
|
Transfer Initial Comment Period | 6/29/2021 | 7/29/2021 |
|
Draft PD Issued | 7/3/2024 | 7/3/2024 |
|
PD Issued | 2/27/2025 | 2/27/2025 |
|
PD Weekly Public Notice | 3/4/2025 | 3/4/2025 |
|
Final Order Issued | 4/2/2025 | 4/2/2025 |
|
Certificate Remaining Issued | 4/2/2025 | 4/2/2025 |
RR 98204 Issued Supersedes CERT 5245
|
Certificate Remaining Issued | 4/2/2025 | 4/2/2025 |
RR 98205 Issued Supersedes CERT 51027
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|