| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/14/2021 | 6/14/2021 |
|
| WMR Request | 6/23/2021 | 9/2/2021 |
|
| Transfer Initial Comment Period | 6/29/2021 | 7/29/2021 |
|
| Final Order Issued | 10/6/2021 | 10/6/2021 |
|
| CBU Received | 8/23/2022 | 8/23/2022 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| Proof to the Satisfaction | 3/21/2023 | 3/21/2023 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|