| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/14/2021 | 6/14/2021 |
|
| WMR Request | 6/23/2021 | 7/20/2021 |
|
| Transfer Initial Comment Period | 6/29/2021 | 7/29/2021 |
|
| Final Order Issued | 10/6/2021 | 10/6/2021 |
|
| Extension Application Received | 9/30/2022 | 9/30/2022 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| Extension FO Issued | 10/19/2022 | 10/19/2022 |
|
| CBU Received | 9/18/2023 | 9/18/2023 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|
| Proof to the Satisfaction | 8/2/2024 | 8/2/2024 |
|
| Extended Completion Date [Extension C Date] | 10/1/2024 | 10/1/2024 |
|
| CBU Due | 10/1/2025 | 10/1/2025 |
|