| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/22/2021 | 6/22/2021 |
|
| WMR Request | 6/29/2021 | 9/9/2021 |
|
| Transfer Initial Comment Period | 7/6/2021 | 8/5/2021 |
|
| Certificate Remaining Issued | 10/18/2021 | 10/18/2021 |
RR Cert 96019 Issued supersedes Cert 74271
|
| Final Order Issued | 10/18/2021 | 10/18/2021 |
|
| CBU Received | 8/22/2022 | 8/22/2022 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| Proof to the Satisfaction | 11/16/2023 | 11/16/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|