| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/30/2021 | 7/30/2021 |
|
| GW Review Request | 9/1/2021 | 1/7/2022 |
|
| WMR Request | 9/1/2021 | 9/16/2021 |
|
| Reimbursement Authority | 9/2/2021 | |
|
| Transfer Initial Comment Period | 9/7/2021 | 10/7/2021 |
|
| RA Applicant Agreement | 10/8/2021 | 10/8/2021 |
|
| Deficiency Letter | 3/28/2022 | 4/30/2022 |
|
| RA Applicant Agreement | 4/15/2022 | 4/15/2022 |
|
| News $ Due Letter | 2/23/2024 | |
|
| Permit Superseding Issued | 5/2/2024 | 5/2/2024 |
Permit G-18904 Issued Supersedes Permit G-15191
|
| Final Order Issued | 5/2/2024 | 5/2/2024 |
|