Process Step | Date Initiated | Date Completed | Comments |
Received | 9/20/2021 | 9/20/2021 |
|
Reimbursement Authority | 9/20/2021 | 7/27/2022 |
|
WMR Request | 9/29/2021 | 1/4/2022 |
|
Transfer Initial Comment Period | 10/5/2021 | 11/4/2021 |
|
RA Applicant Agreement | 10/28/2021 | 10/28/2021 |
|
Draft PD Issued | 3/29/2022 | 3/29/2022 |
|
PD Issued | 6/8/2022 | 6/8/2022 |
|
PD Weekly Public Notice | 6/14/2022 | 6/14/2022 |
|
Final Order Issued | 7/27/2022 | 7/27/2022 |
|
Certificate Remaining Issued | 8/2/2022 | |
RR Cert 96206 issued supersedes cert 81319
|
CBU Received | 9/30/2022 | 9/30/2022 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|