| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/15/2021 | 10/15/2021 |
|
| WMR Request | 11/3/2021 | 8/18/2023 |
|
| Transfer Initial Comment Period | 11/9/2021 | 12/9/2021 |
|
| Draft PD Issued | 3/8/2024 | 3/9/2024 |
|
| News $ Due Letter | 7/25/2024 | |
|
| PD Issued | 8/22/2024 | 8/22/2024 |
|
| PD Weekly Public Notice | 8/27/2024 | 8/27/2024 |
|
| Final Order Issued | 10/18/2024 | 10/18/2024 |
|
| Certificate Remaining Issued | 10/18/2024 | 10/18/2024 |
RR 97871 Issued Supersedes CERT 91208
|
| CBU Received | 9/3/2025 | 9/3/2025 |
|
| Certificate Confirming Issued | 12/12/2025 | 12/12/2025 |
|
| Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
| CBU Due | 10/1/2027 | 10/1/2027 |
|