Process Step | Date Initiated | Date Completed | Comments |
Received | 12/9/2021 | 12/9/2021 |
|
GW Review Request | 12/28/2021 | 2/3/2022 |
|
ODFW Review | 12/28/2021 | 1/4/2022 |
|
Transfer Initial Comment Period | 12/28/2021 | 1/27/2022 |
|
WMR Request | 12/28/2021 | 3/14/2023 |
|
Reimbursement Authority | 12/29/2021 | 9/12/2023 |
|
RA Applicant Agreement | 1/10/2022 | 1/10/2022 |
|
Draft PD Issued | 4/28/2023 | 5/30/2023 |
|
News $ Due Letter | 6/20/2023 | 9/12/2023 |
|
PD Issued | 7/6/2023 | 7/6/2023 |
|
PD Weekly Public Notice | 7/11/2023 | 7/11/2023 |
|
Final Order Issued | 9/12/2023 | 9/12/2023 |
|
Certificate Remaining Issued | 9/12/2023 | 9/12/2023 |
RR Cert 97219 issued superssedes Cert 87964
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
Extension Application Received | 11/15/2024 | 11/15/2024 |
|
Extension FO Issued | 2/5/2025 | 2/5/2025 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|
Extended Completion Date [Extension C Date] | 10/1/2029 | 10/1/2029 |
|
CBU Due | 10/1/2030 | 10/1/2030 |
|