| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/25/2022 | 2/25/2022 |
|
| Transfer Initial Comment Period | 3/8/2022 | 4/7/2022 |
|
| WMR Request | 3/8/2022 | 3/31/2022 |
|
| Draft PD Issued | 9/23/2022 | 9/23/2022 |
|
| News $ Due Letter | 9/23/2022 | 10/14/2022 |
|
| PD Issued | 11/21/2022 | 11/21/2022 |
|
| PD Weekly Public Notice | 11/22/2022 | 11/22/2022 |
|
| Protest Filed | 12/29/2022 | 7/16/2026 |
|
| Certificate Remaining Issued | 10/8/2026 | 10/8/2026 |
RR 99562 Issued Supersedes Cert 2949
|
| Final Order Issued | 10/8/2026 | 10/8/2026 |
|
| Completion Due (C Date) | 10/1/2028 | 10/1/2028 |
|
| CBU Due | 10/1/2029 | 10/1/2029 |
|