Process Step | Date Initiated | Date Completed | Comments |
Received | 3/21/2022 | 3/21/2022 |
|
WMR Request | 3/29/2022 | 4/11/2022 |
|
Transfer Initial Comment Period | 5/3/2022 | 6/2/2022 |
|
Transfer Initial Comment Period | 7/26/2022 | 8/25/2022 |
|
GW Review Request | 2/7/2023 | 12/19/2023 |
|
Reimbursement Authority | 1/18/2024 | |
|
RA Applicant Agreement | 1/31/2024 | 1/31/2024 |
|
Draft PD Issued | 5/24/2024 | 5/24/2024 |
|
PD Issued | 9/5/2024 | 9/5/2024 |
|
PD Weekly Public Notice | 9/10/2024 | 9/10/2024 |
|
Certificate Remaining Issued | 10/28/2024 | 10/28/2024 |
RR 97942 Issued Supersedes CERT 42955
|
Final Order Issued | 10/28/2024 | 10/28/2024 |
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|