| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/19/2022 | 5/19/2022 |
|
| Reimbursement Authority | 5/19/2022 | 9/28/2022 |
|
| WMR Request | 6/3/2022 | 6/15/2022 |
|
| Transfer Initial Comment Period | 6/7/2022 | 7/7/2022 |
|
| RA Applicant Agreement | 6/23/2022 | 6/23/2022 |
|
| Draft PD Issued | 8/10/2022 | 8/10/2022 |
|
| PD Issued | 8/31/2022 | 8/31/2022 |
|
| PD Weekly Public Notice | 9/6/2022 | 9/6/2022 |
|
| Certificate Remaining Issued | 9/28/2022 | 9/28/2022 |
RR Cert 96677 issued supersedes cert 88973
|
| Final Order Issued | 9/28/2022 | 9/28/2022 |
|
| Completion Due (C Date) | 10/1/2029 | 10/1/2029 |
|
| CBU Due | 10/1/2030 | 10/1/2030 |
|