Process Step | Date Initiated | Date Completed | Comments |
Received | 6/10/2022 | 6/10/2022 |
|
Reimbursement Authority | 6/10/2022 | 2/22/2023 |
|
WMR Request | 6/22/2022 | 8/11/2022 |
|
Transfer Initial Comment Period | 6/28/2022 | 7/28/2022 |
|
RA Applicant Agreement | 8/1/2022 | 8/1/2022 |
|
Draft PD Issued | 11/15/2022 | 11/15/2022 |
|
PD Issued | 2/10/2023 | 2/10/2023 |
|
PD Weekly Public Notice | 2/14/2023 | 2/14/2023 |
|
Final Order Issued | 2/22/2023 | 2/22/2023 |
|
Certificate Remaining Issued | 2/22/2023 | 2/22/2023 |
RR Cert 96943 issued supersedes cert 20699.
RR Cert 96942 issued supersedes cert 14576.
|
CBU Received | 8/17/2023 | 8/17/2023 |
|
Completion Due (C Date) | 10/1/2028 | 10/1/2028 |
|
CBU Due | 10/1/2029 | 10/1/2029 |
|