Process Step | Date Initiated | Date Completed | Comments |
Received | 6/27/2022 | 6/27/2022 |
|
WMR Request | 7/7/2022 | 8/1/2022 |
|
Transfer Initial Comment Period | 7/12/2022 | 8/11/2022 |
|
Draft PD Issued | 6/28/2023 | 6/28/2023 |
|
PD Issued | 5/13/2024 | 5/13/2024 |
|
PD Weekly Public Notice | 5/14/2024 | 5/14/2024 |
|
Certificate Remaining Issued | 6/26/2024 | 6/26/2024 |
RR 97223 Issued Supersedes CERT 96136
|
Final Order Issued | 6/26/2024 | 6/26/2024 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|