| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/9/2022 | 9/9/2022 |
|
| Reimbursement Authority | 9/9/2022 | 4/5/2023 |
|
| WMR Request | 9/16/2022 | 10/13/2022 |
|
| Transfer Initial Comment Period | 9/20/2022 | 10/20/2022 |
|
| RA Applicant Agreement | 10/7/2022 | 10/7/2022 |
|
| Draft PD Issued | 12/21/2022 | 1/9/2023 |
|
| PD Issued | 2/22/2023 | 2/22/2023 |
|
| PD Weekly Public Notice | 2/28/2023 | 2/28/2023 |
|
| Final Order Issued | 4/5/2023 | 4/5/2023 |
|
| Certificate Remaining Issued | 4/5/2023 | 4/5/2023 |
RR 96919 Issued Supersedes Cert 86736
RR 96920 Issued Supersedes Cert 87026
|
| Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
| CBU Received | 7/18/2025 | 7/18/2025 |
|
| CBU Due | 10/1/2025 | 10/1/2025 |
|